Marsh Boardwalk
WORK RESUMES
Work started again on Monday February 23, 2009 on Phases Three and Four of the Marsh Boardwalk.
Volunteers are bringing in materials while the ground is frozen and the ice is thick enough to carry the weight. Work on teaching zone three will begin this week, as this area will be covered by deep water once the spring thaw starts.
If you still need to work off that Christmas excess, please call Bill Wilson on 613 475 1554 and join our volunteers.